Wells Street New Construction

PROJECT

Wells Street New Construction (PW14-001)

ENGINEER

City of Kilgore Engineering Department

CONTRACTOR

City Construction Crew

CONSTRUCTION COST

$115,000.00

FUNDING SOURCE

General Fund Balance

PROJECT LOCATION

Wells St. From MLK Dr. to W. North St.

PROJECT SCHEDULE

2017

PROJECT DESCRIPTION

Construct new roadway with curb and gutter, new water, new sewer.

JUSTIFICATION

Currently, no formal roadway exists in this area, but extensive illegal dumping occurs here on a regular basis. Construction of this roadway will improve north-south traffic flow from 4th Street to Martin Luther King Blvd, and expand developable area for new housing.

PROJECT UPDATE

The road right of way has been cleared and the project is currently on hold until other projects are completed first.